Everything Prepared for Subway Construction – Stations to be Built First, Followed by Tunnels
According to him, around 1.5 million cubic meters of the material will be spent, of which 1.2 million cubic meters of sand. This is followed by the successive construction of the depot facilities. Kantar reminds that, on an area of 72 hectares, the management building, the inspection hall for the examination of trains, the halls for the washing of trains and the interventions on wheels, the halls for maintenance and storage of trains, the halls for construction machines and maintenance, the tracks and the new traffic routes are all to be built.
The agreement on the designing for the second phase of the first line has been signed as well, and, as Kantar says, when the preliminary project for the first line is finished in April 2022, negotiations about its construction will start.
– The construction begins with the construction of the stations and several of them should be built so that the TBM machine could pass through. The station at the Republic Square is deeper and takes more time to build, and the machine will quickly travel the distance from there to the Bajloni Market. The construction of the stations will take up to two and a half years overall. For us, it is important for the construction part for the TBM machine to be finished, but it’s inevitable that several stations will be built simultaneously. It is a well-defined plan dynamic. One machine will set off from Makis, the other from Karaburma, and the excavations are to be done at the Mostar station – Kantar told Novosti.
He adds that the stations are to be built in two ways.
– On the Republic Square, the station will be located at the park near Staklenac. We will fence off the space, move the traffic if necessary and we are beginning the excavations. That is the “bottom-up” model. A hole is dug, which remains open throughout, in its full capacity, and the elements are then assembled together. In Pozeska Street, we will most likely implement the “top-down” model. A hole is opened, an upper plate is made, and the construction continues down to the ground through the openings. That is more expensive and takes more time, but takes up less space on the surface – he says.
Naš izbor
Designing of New BG Voz Line to Begin – Stations in Makis and Karaburma, New Railroad Beneath Vidikovac and Route from Vracar Tunnel Planned Građevina, Saobraćaj
Top priče
18.04.2024. | Industrija, Finansije
Strickland Metals has entered the “profitable Serbian gold game”, having set aside 37 million dollars for the purchase of the Rogozna project, which boasts an enormous resource of 5.44 million ounces of gold equivalent (around 170 tons), Australian media report. The Australian giant Strickland Metals Limited is in the business of detecting world-class mineralized systems with a focus on gold and copper. As the media report, Strickland
16.04.2024. | News
Economy Fair in Mostar opens – 26 companies from Serbia exhibiting
16.04.2024. | News
18.04.2024. | Saobraćaj
Jovanovic: Purchase of Siemens trams produced in Kragujevac for GSP Beograd should be considered
18.04.2024. | Saobraćaj
18.04.2024. | Industrija, Saobraćaj
Air Serbia: Eighth ATR 72-600 arrives to Belgrade, expected to join operations soon
18.04.2024. | Industrija, Saobraćaj
eKapija+
18.04.2024. | News
CBRE confirmed its leadership position with Hat-Trick at the 19th SEE Real Estate Awards
18.04.2024. | News
18.04.2024. | News
Consensual termination of employment relationship – News in the court practice?
18.04.2024. | News
18.04.2024. | Građevina
New dimension of life in the part of Belgrade which is waking from sleep (PHOTO)
18.04.2024. | Građevina
17.04.2024. | Saobraćaj
Milsped Group to establish direct rail line between China and Serbia
17.04.2024. | Saobraćaj